Texas LoanSTAR Monitoring and Analysis Program: Report to the Monitoring and Analysis Review Committee
(Energy Systems Laboratory (http://esl.tamu.edu), Texas A&M UniversityDepartment of Mechanical Engineering, Texas A&M University, 1993)
Texas LoanSTAR Monitoring and Analysis Program: Report to the Monitoring and Analysis Review Committee, August 1991 (Volume I)
(Energy Systems Laboratory (http://esl.tamu.edu), Texas A&M UniversityDepartment of Mechanical Engineering, Texas A&M University, 1991)
The LoanSTAR program has now completed its second prototype year. This report is Volume I of a two volume set that documents the progress since the January 1991 MARC meeting. This first voume contains photocopies of the ...
Audit of Lone Star Gas Invoices and Billing Procedures, Task #3
(Energy Systems Laboratory (http://esl.tamu.edu), Texas A&M University, 1997)
At the request of the TAMU Power Plant, the ESL staff audited the 1995 Lone Star Gas
Company invoices. Gas consumption is measured and the measured volume is converted to standard
volume (at T=60 °F, P= 14.65 psia) to ...
Prairie View A&M University Whole Campus Energy Report Update
(Energy Systems Laboratory (http://esl.tamu.edu), Texas A&M UniversityDepartment of Mechanical Engineering, Texas A&M University, 1992)
Prairie View A&M University started a large scale energy management program in 1987 and 1988. This
updated report presents an analysis of whole-campus energy consumption at the Prairie View A&M Campus
where whole-campus ...
Improving Building Energy System Performance by Continuous Commissioning
(Energy Systems Laboratory (http://esl.tamu.edu), Texas A&M UniversityDepartment of Mechanical Engineering, Texas A&M University, 1996)
The term Continuous Commissioning (CC) was first used by engineers at the Energy Systems Lab (ESL) at Texas A&M University to describe an ongoing process which improves the operation of buildings using measured hourly ...
Report of Energy Efficiency Study and Metering/Utilities Profile for Electricity Deregulation at Prairie View A&M University (PVAMU) Prairie View, Texas
(Energy Systems Laboratory (http://esl.tamu.edu), Texas A&M University, 1999)
The physical plant director and staff at Prairie View A&M University (PVAMU) do a good job of maintaining PVAMU facilities and keeping expenses down. During our visit, however, we were able to identify several opportunities ...
Radiant Barrier Performance during the Heating Season
(Energy Systems Laboratory (http://esl.eslwin.tamu.edu), 1992-05)
Results of winter experiments conducted in Central Texas are presented. The experiments were side-by-side tests using two identical 144 ft2 houses which responded similarly to weather variations prior to any retrofits. Two ...
Cool Storage Applications in the Texas LoanSTAR Program: Overview and Preliminary Results
(Energy Systems Laboratory (http://esl.tamu.edu), 1995-03)
The Texas LoanSTAR Monitoring and Analysis Program: Report to the Monitoring and Analysis Review Committee, August 1991 (Volume II)
(Energy Systems Laboratory (http://esl.tamu.edu), Texas A&M UniversityDepartment of Mechanical Engineering, Texas A&M University, 1991)
The LoanSTAR program has now completed its second prototype year. This report
is Volume II of a two volume set that documents the progress since the January 1991
MARC meeting.
This second volume contains papers and ...