dc.description.abstractA thermal storage system was installed in a 37,000 ft2 hospital in April 1992. The chiller had to be operated every summer during peak demand periods until the authors rehabilitated system through building commissioning in late 1995. This paper presents information about the building systems, commissioning activities, and the measured energy savings which resulted from the process.en
dc.publisherEnergy Systems Laboratory (http://esl.tamu.edu)
dc.publisherTexas A&M University (http://www.tamu.edu)
dc.titleRehabilitating A Thermal Storage System Through Commissioningen