Continuous Commissioning Results Verification and Follow-up For an Institutional Building: A Case Study
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2002)
The Kleberg Building on the Texas A&M
University campus is a teaching/research facility
consisting of classrooms, offices and laboratories,
with a total floor area of approximately 165,030 ft2.
Continuous Commissioning ...
The Cost-Effectiveness of Continuous Commissioning® Over the Past Ten Years
(Energy Systems Laboratory (http://esl.tamu.edu), 2008-10)
Continuous Commissioning® data including savings, costs, and implemented measures from over 60 buildings and sites commissioned by staff from the Energy Systems Laboratory at Texas A&M University are presented. Measured ...
Improving Building Comfort and Energy Savings of the McKenzie Airport Terminal by Maintaining and Improving Pneumatic Control Systems
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2004)
McKenzie Airport Terminal is located at
Easterwood Airport, which is owned and
operated by Texas A&M University. It was built
in 1988. Most all HVAC equipment, which
includes boiler, chiller, pumps, AHUs and
exhaust fans, ...
Lessons Learned From the Continuous Commissioning of a Multi-Functional Commercial Building
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2000)
A multi-functional institutional building often
has ventilation and comfort requirements that vary
widely from zone to zone. When we commissioned
the Reed McDonald building on the main campus of
Texas A&M University (TAMU), ...
Baseline Report for the Fort Hood Army Base: Sept. 1, 2002 - Aug. 31, 2003
(Energy Systems Laboratory (http://esl.tamu.edu), Texas A&M University, 2003)
This report presents electricity, natural gas and cooling baselines for the thermal plant, buildings located in the 87000 block, III Corp building and other buildings that were determined to be part of the ESPC project at ...
The Temperature and Relative Humidity Control in Cushing Library
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2002)
Cushing Library located on TAMU campus is a
special building, which needs precise temperature
and relative humidity control, because it stores a
number of rare collections and memorial books.
There are five air-handling ...
The Brazos Valley Energy Conservation Coalition, Part of the Rebuild America Program in Texas: Program Update
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2000)
The Rebuild America program is network of
community-based partnerships that rebuilds
communities by promoting the efficient use of
energy. Rebuild America is coordinated at the
national level by sponsorship through the ...
LoanSTAR after 11 Years: A Report on the Successes and Lessons Learned from the LoanSTAR Program
(Energy Systems Laboratory (http://esl.tamu.edu), Texas A&M University, 2002)
The Texas LoanSTAR (Loans to Save Taxes And Resources) Program was established in 1988 by the Texas Governor’s Energy Office (GEO) as a revolving loan program for funding energy conserving retrofits in state and local ...
A Twelve Year, $10 Million Energy Initiative Marching On: the Texas A&M University Campus Energy Systems CC®
(Energy Systems Laboratory (http://esl.tamu.edu), 2008-10)
The $58.5 million in measured savings for the twelve-year, $10 million continuous commissioning®
(CC®) program at the Texas A&M University (TAMU) makes the decision to continue easy. In today's energy environment and with ...
Investigation of PVC Pipe Failure at Terrell State Hospital – Final Report
(Energy Systems Laboratory (http://esl.tamu.edu), Texas A&M University, 2000)
At the request of Terrell State Hospital and MHMR, the Energy Systems Laboratory at Texas A&M University investigated the failure of the PVC pipes serving the chilled water loop at Terrell State Hospital. There were two ...