dc.description.abstract | Two mission critical electric motor driven BFW (Boiler Feed Water) pumps installed in remote site, facedcontinuous failures of rotor-stator seizures during commissioning and start up of Sulfur recovery units -Pumps had to be refurbished many times at service center by shifting from site and complete dismantling One of the Electric Motor faced several months of outage , bent rotor due to start up attempts These activity posed critical concern over project completion schedule | |
dc.format.medium | Electronic | |
dc.format.mimetype | application/pdf | |
dc.language.iso | en | |
dc.publisher | Turbomachinery Laboratory, Texas A&M Engineering Experiment Station | |
dc.relation.ispartof | Asia Turbomachinery & Pump Symposia. 2021 Proceedings | |
dc.title | CS04: Mitigation of perennial seizure of boiler feed water pumps during commissioning of refinery unit | |