Now showing items 1-3 of 3

    • Houcek, J. K.; Claridge, D. E.; Haberl, J. S. (Energy Systems Laboratory (http://esl.tamu.edu), Texas A&M University; Department of Mechanical Engineering, Texas A&M University, 1993)
      As a part of the Energy Cost Reduction Measure (ECRM) retrofit program, funded by LoanSTAR, the U.T. Arlington site was granted a $2 million loan to implement an energy-saving lighting retrofit in 20 classroom buildings ...
    • Haberl, J. S.; Bou-Saada, T. E.; Vajda, E. J.; Shincovich, M.; D'Angelo III, L.; Harris, L. (Energy Systems Laboratory (http://esl.tamu.edu), Texas A&M University; Department of Mechanical Engineering, Texas A&M University, 1994)
      In September of 1993 a 36,832 fixture lighting retrofit was completed at the United States Department of Energy Forrestal complex in Washington, D.C. This retrofit represents DOE's largest project to date that utilizes a ...
    • Haberl, J. S.; Bou-Saada, T. E. (Energy Systems Laboratory (http://esl.tamu.edu), Texas A&M University; Department of Mechanical Engineering, Texas A&M University, 1995)
      This report provides an overview of the lighting retrofit and the resultant electricity and thermal savings. It presents results from the whole-building monitoring effort that show that the measured gross electricity savings ...