Continuous Commissioning Results Verification and Follow-up For an Institutional Building: A Case Study
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2002)
The Kleberg Building on the Texas A&M
University campus is a teaching/research facility
consisting of classrooms, offices and laboratories,
with a total floor area of approximately 165,030 ft2.
Continuous Commissioning ...
Improving Building Comfort and Energy Savings of the McKenzie Airport Terminal by Maintaining and Improving Pneumatic Control Systems
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2004)
McKenzie Airport Terminal is located at
Easterwood Airport, which is owned and
operated by Texas A&M University. It was built
in 1988. Most all HVAC equipment, which
includes boiler, chiller, pumps, AHUs and
exhaust fans, ...
Results of CC Follow-Up in the G. Rollie White Building
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2002)
An investigation into the increase of energy
consumption of G. Rollie White Coliseum was part
of the persistence project[1], which investigates the
savings in energy consumption of ten buildings that
were commissioned by ...
Correcting Thermal Distribution Problems for a Large University Campus
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2002)
Texas A&M University main campus in
College Station consists of 114 buildings served by
two central plants. The two main campus loops are
more than 50 years old with a total piping length for
each loop in excess of 13 ...