Control Humidity With Single-Duct, Single-Zone, Constant Air Volume System
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2000)
The lecture hall of the Richardson Petroleum
Building at Texas A&M University is a large lecture
hall, with a total floor area of approximately 2500 ft^2.
The lecture hall was served by a constant air volume
(CAV) air ...
Continuous Commissioning Results Verification and Follow-up For an Institutional Building: A Case Study
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2002)
The Kleberg Building on the Texas A&M
University campus is a teaching/research facility
consisting of classrooms, offices and laboratories,
with a total floor area of approximately 165,030 ft2.
Continuous Commissioning ...
Procedures for Filling Short Gaps in Energy Use and Weather Data
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2000)
Filling short gaps (a few hours) in hourly
energy use and weather data can be useful for (i)
retrofit savings analysis and calculation, and for (ii)
diagnostic purposes. The paper evaluates four
methods for rehabilitating ...
Replacing Inefficient Equipment - An Engineering Analysis to Justify Purchasing A More Efficient Chiller
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2005)
Correcting Thermal Distribution Problems for a Large University Campus
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2002)
Texas A&M University main campus in
College Station consists of 114 buildings served by
two central plants. The two main campus loops are
more than 50 years old with a total piping length for
each loop in excess of 13 ...
Shut Down Schedule Optimization with Outdoor Humidity Level
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2006)
Lessons and Measures Learned from Continuous Commissioning(SM) of Central Chilled/Hot Water Systems
(Energy Systems Laboratory (http://esl.tamu.edu)Texas A&M University (http://www.tamu.edu), 2001)
As it has been proved repeatedly that
commissioning is very necessary for new construction
and renovation/retrofit projects, we found continuous
commissioningSM (CC) is an effective and efficient
way to manage and optimize ...