Baseline Report for the Fort Hood Army Base: September 2003 to October 2004
Loading...
Date
2007-09-21
Authors
Journal Title
Journal ISSN
Volume Title
Publisher
Abstract
This report presents electricity, natural gas and cooling baselines for the Thermal Plant, III Corp building,
Darnall Hospital, Main Substation, West Substation, and North Substation.
The baselines developed for this report include data measured during the period from September 2003 through
October 2004. The energy consumption data are presented in time series plots or scatter plots versus ambient
temperature. Baseline are also presented for the natural gas consumption for the Ft. Hood Army base and for
individual channels and groups of channels that represent loads determined to be of value to Ft. Hood.
An appendix is also provided that includes information about ESL’s Channel Identification Tables, data logger
parameter sets, and includes a list of data files in the CDROM that accompanies this report.