Visit the Energy Systems Laboratory Homepage.
Continuous Commissioning® Opportunities in Hospital and Laboratory Facilities
Loading...
Date
2008-10
Journal Title
Journal ISSN
Volume Title
Publisher
Energy Systems Laboratory (http://esl.tamu.edu)
Abstract
This paper compiles the Continuous Commissioning® (CC®) costs, savings, and opportunities implemented in 20 hospital and laboratory commissioning projects involving 48 buildings. The potential savings and costs from 25 CC assessments of 36 buildings are also analyzed and compared with the results of the implemented projects. The results from these projects including deficiencies and commissioning measures identified, and the cost and savings associated with CC are discussed. Case studies are also presented.
For the 20 completed hospital and laboratory CC projects, the median (average) pre-CC energy cost was $3.44/ft2 ($4.46/ft2) [$36.98/m2 ($48.06/m2)] with median (average) energy cost savings of $0.84/ft2 ($1.19/ft2) [$9.03/m2 ($12.80/m2)] or 20% (26%). The median (average) potential savings identified in the 25 CC assessments were $0.41/ft2 ($0.44/ft2) [$4.36/m2 ($4.72/m2)] or 15% (16%). The lower savings identified in the assessments may result from the conservatism inherent in an incomplete identification of all potential measures during the assessments, or may result from some other factor.
Description
Keywords
Continuous Commissioning, Costs and Savings, Hospitals and Laboratories