Show simple item record

Visit the Energy Systems Laboratory Homepage.

dc.creatorHaberl, J. S.
dc.creatorLiu, Z.
dc.date.accessioned2007-09-21T21:08:23Z
dc.date.available2007-09-21T21:08:23Z
dc.date.issued2007-09-21
dc.identifier.otherESL-TR-04-12-02
dc.identifier.urihttps://hdl.handle.net/1969.1/6055
dc.description.abstractThis report presents electricity, natural gas and cooling baselines for the Thermal Plant, III Corp building, Darnall Hospital, Main Substation, West Substation, and North Substation. The baselines developed for this report include data measured during the period from September 2003 through October 2004. The energy consumption data are presented in time series plots or scatter plots versus ambient temperature. Baseline are also presented for the natural gas consumption for the Ft. Hood Army base and for individual channels and groups of channels that represent loads determined to be of value to Ft. Hood. An appendix is also provided that includes information about ESL’s Channel Identification Tables, data logger parameter sets, and includes a list of data files in the CDROM that accompanies this report.en
dc.format.extent8440347 bytesen
dc.format.mimetypeapplication/pdf
dc.language.isoen_US
dc.relation.ispartofseriesESL-TR-04-12-02
dc.titleBaseline Report for the Fort Hood Army Base: September 2003 to October 2004en
dc.typeTechnical Reporten


This item appears in the following Collection(s)

Show simple item record