Visit the Energy Systems Laboratory Homepage.
Rehabilitating A Thermal Storage System Through Commissioning
Abstract
A thermal storage system was installed in a
37,000 ft2 hospital in April 1992. The chiller
had to be operated every summer during peak
demand periods until the authors rehabilitated
system through building commissioning in late
1995. This paper presents information about the
building systems, commissioning activities, and
the measured energy savings which resulted
from the process.
Citation
Liu, M.; Veteto, B.; Claridge, D. E. (1998). Rehabilitating A Thermal Storage System Through Commissioning. Energy Systems Laboratory (http://esl.tamu.edu); Texas A&M University (http://www.tamu.edu). Available electronically from https : / /hdl .handle .net /1969 .1 /6739.